Burgiss
Design Brief
- Take raw site of 1020m2 spread over 2# floors – do design – 3 d’ proposals and presentations to client.
- Compile all drawings, details and specification for council submission and obtain final occupation Certificate.
- Provide detailed project construction time line schedule and carry out all aspects of build work in accordance with detailed specifications and in line with time lines set.
- Set up and link 2 large sever rooms and connect all desking to sophisticated internet access.
- Design and apply all signage requirements, colours and parking pay signage.
- Design, supply and install external covers and furniture.
- Design, construct two fully equipped canteens and kitchen / staff chill areas.
- Hand over completed project to client on time and on budget.
Project Details
- Client - Infusion Office Concepts
- Location - Stellenbosch
- Budget - Final cost for the build R3.5 million
- Duration - 8 Weeks